Alt-FEMPs Now Complete

Alt-FEMP participants to submit final invoices by August 31, 2025.

The objectives of the alt-FEMP delivery component were:

Eligibility

Program Funding

Eligible Alt-FEMP Cost Elements

Program Duration

Data Management

Scoring Rubric

 Alt-FEMP Readiness LevelFormative stagesArea defined with participants and facilities. Application not yet startedHold all required elements for AER Directive 60 alt-FEMP proposal submission including equivalency modelling but not submitted to AER for approvalAlt-FEMP approved and wanting to continue existing program or retroactive fundingAlt-FEMP approved and additional companies already signed on to participate5%
Note: Funding will not be issued until the alt-FEMP is approved by AER
CollaborationDo not want to collaborate Yes to Collaboration but parties or area(s) not yet identifiedYes to collaboration interested parties identified but no group formedYes to collaboration, participants preparing to sign onOrganized group in place and all are willing to collaborate.  Group has containers and equipment list in place10%
Data SharingNot willing to share data but will provide elements of data to program Willing to provide summary data by program element (screening, survey, repair) embargoedWilling to share data with embargoes stricter than outlined by AMEP programWilling to share data with embargoes outlined by AMEP program Willing to share data with no embargo20%
Emission Reduction EquivalencyEmission reduction equal or 10% below baseline   Emission reduction equal to baseline or up to 9% below baselineEmission reduction modelled to be above baseline – performance not yet validatedEmission reduction above baseline programEmission reduction above baseline program and  committed budget dollars to a voluntary vent reduction program20%
Economic EquivalencyWithin +25% of baseline  Within +15% of baselineWithin +5% of baseline EquivalentBelow baseline10%
Technology VarianceSingle technology no change to methodSingle technology updated method Multiple technologies or updated methodExisting technology MDL lowered and limitations reducedNew Technology or method; combination of technologies providing research answers10%
Technology Rating (Screening)< TRL 7 TRL is 8TRL is 8 and field trials are neededTRL is 9 but still needs CRT testingTRL is 9 and full rounds of CRT are completed with results available.7%
Technology Rating (Survey)< TRL 7 TRL is 8TRL is 8 and field trials needed TRL is 9 but still needs CRT testing TRL is 9 and full rounds of CRT are completed with results available.3%
Technology Home BaseOutside of North America North America with no Canadian officeNorth America with office in CanadaCanadaAlberta with offices in the province5%
Alt-FEMP Startup>Q2 2023 Q2 2023Q1 2023Prior to December, 2022Prior to July, 20227%
Facility Frequency (3 x & 1 x)3 x per year onlyBoth 1x and 3x per year survey facilities included within Alt-FEMP area3%